REPORT ON STATUS OF PROJECTS AT THE SECOND QUARTER (2025)

INTRODUCTION

This report seeks to provide an overview of the projects undertaken by the Municipal Assembly during the second quarter of the year. The aim is to inform stakeholders, including community members about the assembly’s commitment to enhancing the quality of life within the municipality.

OVERVIEW

In the second quarter, the projects undertaken have seen some improvement.  Among these projects are;

  • The completion of 1No. 2 storey Health Facility at Gbetsile which is 30% completed.
  • Construction of 3Unit kindergarten block with ancillary facility at Nii Oglie which has been 100% completed.
  • Completion of 1No. Dormitory Block at Kpone Senior High School which is 98% complete.
  • Completion of 1No. 2-Storey Police Station at Oyibi which has been 100% completed.
  • Construction of No.1 2 storey 6-unit classroom block with Ancillary facility (Ground floor) at Nanoman which is 95% complete.
  • Construction of Community-Based health planning and Services (CHPS) Compound at Nmlitsakpo and is 100% complete.
  • Construction of a new market at Kpone which is 60% complete.

CONCLUSION

The second quarter has seen progress across the various projects undertaken by the Assembly.

 

Item

Project Description

Development

Dimension

 Location

Contractor/Consultant

Contract Sum GH¢

 

Source of Funding

Date of Award

 

Date Start

Expected Date of Completion

Expenditure to date GH¢

 

Outstanding Balance

 Implementation Status (%)

1

Completion of 1No. 2 Storey Health Facility at Gbetsile

Health

Gbetsile

Selyn Company Ltd.

1,787,007.60

DACF/IGF

11/9/24

 

12/9/2025

 

 

30% completed, plastering works & P.O.P ceiling ongoing

2

Construction of 3Unit kindergarten block with ancilliary facility

Education

Nii Oglie

 LNJ Lopez Company     Limited

306,528.60

DACF

6/9/19

30/6/2020

24/9/2022

124,939.35

181,589.25

100% completed and in use

 

 

3

Completion of 1No, Dormitory Block at Kpone Senior High School

Education

Kpone

Emmcud Const. Company Ltd.

974,459.33

DACF

17/9/2024

 

 

 

 

 

 

30/9/2024

17/9/2025

351,936.00

622,523.33

98% completed. Final painting, screeding and connection of plumbing works to the septic tank are done.

4

Completion of 1No. 2-Storey Police Station

Security

Oyibi

SPW Company Ltd.

349,163.55

DACF

19/6/2020

8/7/2020

19/6/2022

207,752.40

141,411.15

Completed and in use.

5

Construction of No.1 2 Storey 6-unit classroom block with Ancillary facility 

Ground floor

Education

Nanoman

 Cobastar mining and construction ltd.

857,728.20

DACF

2/11/2022

24/11/2022

4/11/2023

289,569.60

568,158.60

95% completed. Project plastered and painted, doors and windows fixed. Tiling works in the washroom is yet to commence.

 

 

6

Construction of Community-Based health planning and Services (CHPS) Compound

Health

Nmlitsakpo

Selyn Company Ltd.

730,552.73

DACF

4/5/23

2/8/23

12/1/24

 

 

100% Completed. Water closet and connection of plumbing works to the septic tank is yet to be done.

 

7

Construction of a new market

Social

kpone

Derkak Construction Ltd

9,915,699.02

DACF

5/1/2024

 

5/1/2025

 

 

60% completed. Superstructure works ongoing. First floor block work and lintel done. Block work after lintel ongoing.

 

 

APPENDIX

 

CONSTRUCTION OF A NEW MARKET AT KPONE

COMPLETION OF 1NO, DORMITORY BLOCK AT KPONE SENIOR HIGH SCHOOL

CONSTRUCTION OF NO.1 2 STOREY 6-UNIT CLASSROOM BLOCK WITH ANCILLARY FACILITY GROUND FLOOR AT NANOMAN

CONSTRUCTION OF COMMUNITY-BASED HEALTH PLANNING AND SERVICES (CHPS) COMPOUND AT NLITSAKPO

COMPLETION OF 1NO. 2 STOREY HEALTH FACILITY AT GBETSILE

CONSTRUCTION OF SLAUGHTER SLAB, CONCRETE SLAB, U-DRAIN, SHED A, SHED B, AND FENCE WALL FOR TULAKU KRAAL (SLAUGHTER HOUSE) AT TULAKU