INTRODUCTION
This report seeks to provide an overview of the projects undertaken by the Municipal Assembly during the first quarter of the year. The aim is to inform stakeholders, including community members about the assembly’s commitment to enhancing the quality of life within the municipality.
OVERVIEW
In the first quarter of the year, several key projects were undertaken, focusing on education, health, security and socio-economic infrastructure development. Among these projects are;
- The completion of 1No. 2 storey Health Facility at Gbetsile which is yet to commence.
- Construction of 3Unit kindergarten block with ancillary facility at Nii Oglie which has been completed and is in use but retention has not been released to the contractor.
- Completion of 1No. Dormitory Block at Kpone Senior High School which is 90% complete.
- Completion of 1No. 2-Storey Police Station at Oyibi which has been completed and is in use but retention has not been released to the contractor.
- Construction of No.1 2 storey 6-unit classroom block with Ancillary facility (Ground floor) at Nanoman which is 90% complete.
- Construction of Community-Based health planning and Services (CHPS) Compound at Nmlitsakpo and is 100% complete.
- Construction of a new market at Kpone which is 40% complete.
CONCLUSION
The first quarter has seen progress across the various projects undertaken by the Assembly.
Item |
Project Description |
Development Dimension |
Location |
Contractor/Consultant |
Contract Sum GH¢ |
Source of Funding |
Date of Award |
Date Start |
Expected Date of Completion |
Expenditure to date GH¢ |
Outstanding Balance |
Implementation Status (%) |
1 |
Completion of 1No. 2 Storey Health Facility at Gbetsile |
Health |
Gbetsile |
Selyn Company Ltd. |
1,787,007.60 |
DACF/IGF |
11/9/24 |
|
12/9/2025 |
|
|
Yet to commence |
2 |
Construction of 3Unit kindergarten block with ancilliary facility |
Education |
Nii Oglie |
LNJ Lopez Company Limited |
306,528.60 |
DACF |
6/9/19 |
30/6/2020 |
24/9/2022 |
124,939.35 |
181,589.25 |
100% completed and in use
|
3 |
Completion of 1No, Dormitory Block at Kpone Senior High School |
Education |
Kpone |
Emmcud Const. Company Ltd. |
974,459.33 |
DACF |
17/9/2024
|
30/9/2024 |
17/9/2025 |
351,936.00 |
622,523.33 |
90% completed. Final painting, screeding and connection of plumbing works to the septic tank is yet to be done. |
4 |
Completion of 1No. 2-Storey Police Station |
Security |
Oyibi |
SPW Company Ltd. |
349,163.55 |
DACF |
19/6/2020 |
8/7/2020 |
19/6/2022 |
207,752.40 |
141,411.15 |
Completed and in use. |
5 |
Construction of No.1 2 Storey 6-unit classroom block with Ancillary facility Ground floor |
Education |
Nanoman |
Cobastar mining and construction ltd. |
857,728.20 |
DACF |
2/11/2022 |
24/11/2022 |
4/11/2023 |
289,569.60 |
568,158.60 |
90% completed. Project plastered and painted, doors and windows fixed. Tiling works in the washroom is yet to commence.
|
6 |
Construction of Community-Based health planning and Services (CHPS) Compound |
Health |
Nmlitsakpo |
Selyn Company Ltd. |
730,552.73 |
DACF |
4/5/23 |
2/8/23 |
12/1/24 |
|
|
100% Completed. Water closet and connection of plumbing works to the septic tank is yet to be done.
|
7 |
Construction of a new market |
Social |
kpone |
Derkak Construction Ltd |
9,915,699.02 |
DACF |
5/1/2024 |
|
5/1/2025 |
|
|
40% completed. Superstructure works ongoing. Superstructure block work done and Suspended floor casted.
|